In cities that use the International Residential Code, a deck needs a building permit unless it fits a narrow exemption: 200 square feet or less, no more than 30 inches above grade, not attached to the house, and not serving the required exit door. Local rules can be stricter. Expect to submit a site plan and drawings, then pass inspections.
Updated
Rather not do this yourself? We prepare your deck permit file for your address, and revise it until approved.
Get my permit · $399Key facts
- For decks, all four conditions must be true at the same time: the deck is 200 square feet or less; it is no more than 30 inches above grade at any point; it is not attached to the house; it does not serve the exit door the code requires for the home.[1]City of Federal Way, Washington, Residential permit exemptions
- In Hastings, all decks 30 inches or more above grade must have a guardrail at least 36 inches high.[2]City of Hastings, Minnesota, Deck permit requirements
- In Canandaigua, a 12 by 16 foot deck (192 square feet) works out to $57.60, so the $100 minimum applies.[5]City of Canandaigua, New York, Fee Schedule 2026
- Fairfax County applies its rules on unpermitted construction to homes that were bought and sold, regardless of when the construction was done, so an unpermitted deck can surface when you sell, or when you buy.[3]Fairfax County, Virginia, Department of Code Compliance, Unpermitted Construction
- In New York City, legalizing work done without a permit on a one- or two-family home carries a $600 civil penalty, and removing the work instead carries the same penalty.[7]New York City Department of Buildings, Form L2 instructions, civil penalties for work…

Do you need a permit for your deck?
Start from the exemption, because everything else needs a permit. In the International Residential Code (IRC), Section R105.2 lists the work that does not need one. For decks, all four conditions must be true at the same time[1]:
- the deck is 200 square feet or less;
- it is no more than 30 inches above grade at any point;
- it is not attached to the house;
- it does not serve the exit door the code requires for the home.
Miss one condition and the exemption is gone. A 12 by 16 foot deck is 192 square feet, so it passes on size, but if it is bolted to the house, or stands higher than 30 inches anywhere on a sloping yard, it needs a permit.
| Your deck | Permit under the IRC exemption? |
|---|---|
| Attached to the house with a ledger board | Yes |
| More than 30 inches above grade at any point | Yes |
| Larger than 200 square feet | Yes |
| Serves the required exit door | Yes |
| Small, low, freestanding, no required door | Possibly exempt: check your city first |
The exemption is not a free pass, and it is only the model code. Federal Way, Washington, which publishes the list, adds that separate permits may still be required for exempted items, and that any work in a critical area, such as wetlands, streams or landslide hazard areas and their buffers, is not exempt[1]. Other places go further: Fairfax County, Virginia, names decks and porches among the common projects that need a building permit, along with sheds and other detached structures over 256 square feet, and notes that Virginia law requires both permits and passed inspections[3].
What the city asks for
A deck permit application is mostly drawings. The list from Hastings, Minnesota, is typical of what a building department wants to see[2]:
- A site plan: a scaled drawing that shows where the deck sits on the lot, with its distances from the property lines, utility easements, power lines and other structures.
- A deck plan, with dimensions and materials, covering the footings, the ledger, the beams, the joists, the decking and the stairs.
- An elevation drawing showing how high the deck stands above the ground.
- An owner-contractor waiver if you build the deck yourself.
The site plan is where the city checks the distances between your deck and your property lines. That is why the same deck can be fine on one lot and refused on the next.
Deck permit drawings
The American Wood Council publishes a guide to deck construction, known as DCA 6. It describes a framing plan as the drawing that shows the width, the length, the joist and beam layout, the location of the ledger board, posts and footings, and the type, size and spacing of the ledger board fasteners[6].
DCA 6 has limits worth knowing before you draw anything. It applies to single-level residential wood decks attached to the house to resist lateral forces, and decks supporting large concentrated loads, such as hot tubs, are beyond its scope[6]. A two-level deck or a deck with a hot tub falls outside this guide and may need an engineered design.
Your drawings must also show the guards. In Hastings, for example, all decks 30 inches or more above grade must have a guardrail at least 36 inches high[2].
The inspections
The permit is not the end: the inspector visits during construction. Hastings lists three steps[2]:
- Footings, inspected and approved before any concrete is placed;
- Framing, as a separate inspection for decks under 60 inches above grade;
- Final, which must be completed before the deck can be used.
Plan your work around them: pouring concrete before the footing inspection skips a step the city requires.
What a deck permit costs
Fees are set by each city, and they are published. Two real examples:
| City | Deck permit fee | Source |
|---|---|---|
| Oakdale, Minnesota (2025) | $160 flat, up from $154 in 2024 | 2025 fee schedule[4] |
| Canandaigua, New York (2026) | $0.30 per square foot, $100 minimum | 2026 fee schedule[5] |
In Canandaigua, a 12 by 16 foot deck (192 square feet) works out to $57.60, so the $100 minimum applies[5]. Other permits are often priced on the value of the work: the same Oakdale schedule sets value-based building permits and a plan review fee of 65% of the permit fee for them[4]. Your permit file shows your own city's fee, from its fee schedule, with the link.
How long it takes
There is no national average worth quoting: review times depend on the city, its workload and how complete the application is. What you control is the first submission: an application with a complete site plan and readable drawings avoids the correction requests that restart the clock.
Building without a permit
Skipping the permit does not make the question go away. Fairfax County applies its rules on unpermitted construction to homes that were bought and sold, regardless of when the construction was done[3], so an unpermitted deck can surface when you sell, or when you buy. Fixing it later costs money: in New York City, legalizing work done without a permit on a one- or two-family home carries a $600 civil penalty, and removing the work instead carries the same penalty[7].
Already built your deck?
Talk to your building department before anything else: it decides whether and how work done without a permit can be legalized, and what must be shown, opened up or changed. Expect a cost on top of the normal permit fee: in New York City, legalizing it is the $600 penalty mentioned above[7].
Common questions
How big can a deck be without a permit?
Under the International Residential Code exemption, 200 square feet at most, and only if it is also no more than 30 inches above grade at any point, not attached to the house and not serving the required exit door. Your city can set a lower limit or require a permit for every deck, so check its own rules before you build.
Does a freestanding deck need a permit?
Usually yes, unless it meets every condition of the exemption at the same time, size, height and exit door included. A freestanding deck higher than 30 inches above grade at any point, or larger than 200 square feet, needs a permit under that exemption.
Can I build the deck myself?
Often yes. Hastings, Minnesota, for example, asks homeowners who build their own deck for an owner-contractor waiver with the permit application. You still need the permit, the drawings and the inspections.
What is DCA 6?
A prescriptive guide published by the American Wood Council for single-level residential wood decks attached to the house. Its details for footings, ledgers, joists, beams, guards and stairs are based on the International Residential Code.
Is the city's permit fee included in your price?
No. The permit fee is paid to your city or county. Your permit file shows the fee from your city's published fee schedule, with the link, before you file.
We handle the permit. You build your deck.
- Your city's rule, for your addressThe code section, its link and the date we checked it.
- Site plan and dimensioned drawingsDistances to your property lines, ready for the application.
- The form, where to file it, and the published feePlus the documents list and an HOA request template.
- Reviewed, then revised until approvedWith All-in, after every comment from the city, for up to 6 months.
Sources
- City of Federal Way, Washington, Residential permit exemptions (International Residential Code, Section R105.2). Checked October 13, 2026.
- City of Hastings, Minnesota, Deck permit requirements. Checked October 13, 2026.
- Fairfax County, Virginia, Department of Code Compliance, Unpermitted Construction (September 2024). Checked October 13, 2026.
- City of Oakdale, Minnesota, Ordinance 942, 2025 Fee Schedule. Checked October 13, 2026.
- City of Canandaigua, New York, Fee Schedule 2026. Checked October 13, 2026.
- American Wood Council, Prescriptive Residential Wood Deck Construction Guide (DCA 6), based on the 2015 IRC. Checked October 13, 2026.
- New York City Department of Buildings, Form L2 instructions, civil penalties for work without a permit (rev. 03/2026). Checked October 13, 2026.